Project -
Black Devon Landfill Site, Alloa
- Installation of Capping
Client:Clackmannanshire Council
Engineer:
Jacobs Babtie
Further to the closure of the above site, we were awarded the contract which had a duration of 19 weeks and was completed on schedule and within budget.
Over 200,000 square metres of geo synthetic clay liner was put in place to retain methane gasses.
In addition 100,000 cubic metres of material excavated adjacent to the landfill site was deposited on top creating a seal.
Contract Value: £1.3 million |
|
|