Blyth & Blyth
It was thirsty work but somebody had to do it – extending the existing bottling and distribution facilities at AG Barrs in Cumbernauld that is. During the hottest part of last summer – from May to August – we took over the job when another construction company went into receivership.
Where possible we kept on the existing sub-contractors to see the project through to the end.
Whilst we were carrying out the extension, the facilities remained fully operational.
We worked seven days a week to meet the client’s needs of getting the project completed as quickly as possible.
Contract Value: £2.2 million |
|
|